Date: October 2011
Location: Spokane, Washinton
Weight: 193 tons
Sacred Heart ED Expansion
UW Medicine, Phase 3.1
Date: September 2011
Location: Lake Union, Washington
Weight: 137 tons
Providence Generation Hospital
Date: October 2010
Location:
Weight: 750 tons
Bella Bottega Medical Office Building

Date: February 2010
Location: Redmond, Washington
Weight: 254 tons
Westside Medical Center Utility Plant
Date: January 2010 – In progress
Location: Hillsboro, Oregon
Weight: 217 tons
Redmond Medical Office Building
Date: February 2010 – In progress
Location: Redmond, Washington
Weight: 270 tons
Westside Medical Center (C.U.P.)
Date: January 2010
Location: Hillsboro, Oregon
Weight: 217 tons
St. Peter’s Medical Office Bldg

Date: December 2007
Location: Washington
Weight: 360 tons
Shriners Childrens Hospital
Date completed: November 2007
Location: Honolulu, Hawaii
Weight: 380 tons
Harborview Medical Center
Date completed: September 2005
Location: Seattle, Washington
Weight: 450 tons